Truesdale Lake  

South Salem, New York

Separator Installed – Paving Tomorrow

DSC_0219

Loading the 10 ton separator

The final underground pieces of the “Site 3” puzzle arrived from their casting in New Hampshire and were installed on Tuesday December 1.  The crew came back on Wednesday morning to check the flows and fixed some minor issues.  The paver “Bessie” was delivered this morning (Dec 3) and will be underway tomorrow.

DSC_0234

After the paving is finished, the project will be complete.  Thanks to the guys at Landscape Unlimited for their work and expertise over the past 2 months.  Also thank you to Ryan and Daniel from Keller and Sessions (our town engineering firm) for their advice and keeping the project on track.

Site 3 is almost done!  Next up – sites 1, 2, 4, 5, and 6!

Click “Continue Reading…” below to see the complete photo gallery.

Comments are closed.